St Margaret School, Lowestoft
Project name: St Margaret School, Lowestoft
M&E Order Value: £400k
Contractor: Kier
Consultant: John Slater and Haward
St Margaret's School was extended and remodelled to accommodate an increased number of teaching spaces over 2 phases.
Phase 1 included the main school works to areas consisting of the Reception, Main Hall, Kitchen and Classrooms.
Phase 2 included the external lighting works. New and altered M&E systems included heating, ventilation, gas, VRF HCWS, above ground drainage, lighting, small power, telephone & data, CCTV, security, fire alarm.