Solihull Community Housing (SCH)
Project name: Heating and Electrical
Client: Solihull Community Housing
M&E Order Value: £3m / annum
Contract Length: 2016-2022
Originally operating as Solihull Community Housing's (SCH) electrical contractor in
2012, due to consistently high levels of service Dodd Group was awarded 100% of the
gas and electrical works in 2014, before successfully re-tendering the entire contract
again in 2016.
We provide planned and 24/365 reactive gas servicing, maintenance, installations,
repairs and electrical testing, repairs, rewires, upgrades and improvements works to
8,300 properties across Solihull.
Cost Efficiencies
• Worked alongside gas engineers to reduce fitting packs; reducing the cost of each
heating installation by 8%
• Replaced filter manufacturer to further reduce heating installation costs by 0.25
• Conducted a pricing exercise with boiler manufacturer to reduce installation costs
by a final 2%
• Reduced gas servicing costs by 9.27% and out of hours heating repair costs by
8.37%, saving £20,000 since January 2017
• Exchange post-installation surplus materials for supplier credit
• Completed an additional 312 EICRs within the allocated electrical budget
• Reduced electrical testing costs by 5.9% overall, by completing first time fix repairs
on category 2 items, preventing return visits
Key Information:
• Long term, Open Book Partnership
• Female Gas Engineer is a full trained Liaison Officer
• Inducted 13 inherited engineers from 2 incumbent contractors via TUPE
• Undertook the gas works 18 months’ early, upon request, mobilising in 2 weeks